What is the issue?
India’s generation glut in electricity has been exacerbated due to stunted demand, which has brought down prices & left investors in the lurch.
What is the background?
- With a pan-India thrust on electrification, the nation has become flush with power generation capacity in the last six to eight months.
- This was further aided by the generation sector delicensing under the Electricity Act, 2003.
- The spurt in “Merchant Market Prices” between 2008 and 2011 led power generation investors to enter the market.
- Now, with excess production, merchant market prices have crashed, which has resulted in power generation companies have leaving their assets stranded.
- Discoms have also become hesitant to undertake long-term power generation contracts that span a five to seven-year period.
- This pricing dichotomy raises several questions.
What is the case for long term agreements?
- Production - Of the total electricity generation of 997 GWH (October 2016), over 90 per cent was sold through long-term contracts, which clearly indicates that merchant prices do not represent correct power prices.
- Power plants have always been set up to meet consumers needs for the long term & therefore, investors have aligned resources for the long term (typically 4 to 5 decades).
- Financial institutions too, assess long-term revenue visibility before lending to investors.
- Transmission -Power transmission is also designed for longevity.
- Transmission networks planned by the CTU and STU are developed to transmit power for 25 years, if not more, to buyers.
- Agreements - Long term agreements make it possible to finance new coal mines, essential for regular fuel access.
- For this, PPAs of long duration are the only win-win solution for both generating companies and consumers.
- This was echoed by the Maharashtra Electricity Regulatory Commission order.
How does the landscape look?
- Historically, power generation has been price-regulated in India.
- The electricity sector received new impetus under the Electricity Act-2003, Competitive Bidding Guidelines-2005, the National Tariff Policy-2006, and other government notifications.
- With the establishment of merchant power plants, investors were expected to shoulder the market risk of volatile selling prices.
- However, not all investors followed this business model and many preferred the regulated route of tariff determination, as it ensures a revenue stream for the duration of the PPA.
What are the concerns of the investors?
- Power Plants need to recover their investments over their economic life.
- This require tariffs to be determined after considering the operating costs, investment and depreciation.
- Owing to short duration of the PPA, there is sizeable investment, which is yet to be recovered.
- Hence, if the “initial” PPA period is less than its economic life, then the remaining period’s tariff should also be based on tariff regulation norms.
- It would be unfair to leave the regulated tariff plants after the initial tariff period “in the lurch”, and expect them to participate in the merchant market for their remaining lifetime.
- This is the only was to protect investor sentiment in the sector and enhance production to meet the growing demand for power.
How will this affesct the consumer?
- The consumer will also benefit from extending the regulated tariff to the balance period, as regulated tariffs are stable.
- At present, merchant tariffs are low due to “suppressed” demand but price fluctuation in future can’t be ruled out.
- While India is trying to move towards more developed international merchant markets, it must avoid compromising the health of the ‘power generation business’.
- One of the ways of ensuring this stability is for the PPA period to match the economic life, that is, 25 years for thermal and 35 years for hydro.
- PPAs can be constructed either through ‘Competitive bidding’ for a 25 year period that ensures predictability or through the regulated route that ensures a viable tariff.
Source: Business Standard