Challenges before Cleaning Ganga

iasparliament Logo
August 02, 2018

Why in news?

National Green Tribunal has summoned union government’s NMCG for its delayed actions in Ganga-cleaning projects.

What is the National Mission for Clean Ganga (NMCG)?

  • It is a registered trust that runs the ‘Namami Gange’ mission, India’s most ambitious endeavour to clean the Ganga River.
  • The NMCG has a Rs. 20,000-crore, centrally-funded, non-lapsable corpus and consists of nearly 288 projects.
  • The NMCG’s thrust is on roping in the private sector to set up sewage treatment plants and also maintain them.
  • In return, the government offers to contribute 40% of the capital costs upfront and disburse the rest with a profit margin over 15 years subject to performance indicators being met.
  • The mission also has projects to clean the Ghats, rid the river of biological contaminants and improve rural sanitation and afforestation.

What is NGT’s decision on clean Ganga mission?

  • Recently the National Green Tribunal was hearing petitions around Ganga-cleaning projects, it pulled up the government for its tardy job.
  • The NGT showed its concerns that the stretches between Haridwar and Unnao were “unfit for drinking and bathing” and that authorities should display “health warnings”.

What are the implementation challenges with this project?

  • Most of the Ganga is polluted and it is due to five States on the river’s main stem Uttarakhand, Uttar Pradesh, Jharkhand, Bihar and West Bengal.
  • Approximately 12,000 million litres a day (MLD) of sewage is generated in the Ganga basin, for which there is currently a treatment capacity of just 4,000 MLD.
  • Industrial pollution from tanneries in Kanpur, distilleries, paper and sugar mills in the Kosi, Ramganga and Kali river catchments is a major contributor.
  • So far, the State governments only have concentrated on superficially cleaning the river by using trash skimmers and improving crematoria-infrastructure.
  • A financial audit also suggested that while Rs. 20,601 crore had been sanctioned for 193 projects, only Rs. 4,254 crore had actually been spent on their implementation.

What is government’s further plan on clean Ganga?

  • Union Water Resources Ministry has promised that 80% of the river will be cleaned by May 2019.
  • The Union Water Resources Ministry has been focussed on ensuring a transparent tendering and bidding process.
  • Only this year have treatment plants at Haridwar and Varanasi begun to be constructed.
  • In May 2014, there were 31 treatment plants with a capacity of 485 MLD. As of May 2018, 94 projects, with a treatment capacity of 1,928 MLD, were under way.

 

Source: The Hindu